SECTION 02832
CONCRETE
SEGMENTAL RETAINING WALL SYSTEM
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Retaining wall system constructed of
concrete segmental retaining wall units.
B. Geosynthetic reinforcement fabric
C. Leveling pad base
D. Drainage aggregate
E. Backfill
F. Drainage
pipe
G. Adhesives
1.02 RELATED SECTIONS
Note to
Specifier: Include Section 01270 only
if Article 3.12 is included
A. Section 01270 - Unit Prices
Note to
Specifier: Include Section 02300 below
for finish grading, and/or add other paving or surfacing related Sections if
required
B. Section 02300 - Earthwork: For finish grading.
1.02 REFERENCES
A. American
Association of State Highway Transportation Officials (AASHTO)
1. AASHTO
M288 Geotextile Specification for Highway Applications
2. AASHTO Standard Specifications
for Highway Bridges
B. American Society for Testing and Materials
(ASTM)
1. ASTM C140 Standard Test Methods
for Sampling and Testing Concrete Masonry Units and Related Units [Last
Update: 01ae1]
2. ASTM
C1262 Standard Test Method for Evaluating the Freeze-Thaw Durability of
Manufactured Concrete Masonry Units and Related Concrete Units [Last Update:
98]
3. ASTM
C1372 Standard Specification for Segmental Retaining Wall Units [Last
Update: 01a]
4. ASTM D448 Standard
Classification for Sizes of Aggregate for Road and Bridge Construction [Last
Update: 98]
5. ASTM
D698 Standard Test Methods for Laboratory Compaction Characteristics of Soil
Using Standard Effort (12,400 ft-lbf/f3)(600 kN-m/m3) [Last
Update: 00a]
6. ASTM
D1556 Standard Test Method for Density and Unit Weight of Soil In Place by the
Sand Cone Method [Last Update: 00]
7. ASTM
D1557 Standard Test Methods for Laboratory Compaction Characteristics of Soil
Using Modified Effort (56,000 ft-lbf/f3)(2700 kN-m/m3) [Last
Update: 00]
8. ASTM D2487 Standard
Classification of Soils for Engineering Purposes (Unified Soil Classification
System) [Last Update: 00]
9. ASTM D2922 Standard Test Methods
for Density of Soil and Soil-Aggregate In Place by Nuclear Methods (Shallow
Depth) [Last Update: 01]
10. ASTM
D3034 Standard Specification for Type PSM Poly(Vinyl Chloride) (PVC) Sewer pipe
and Fittings [Last Update: 00]
11. ASTM
D4318 Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity
Index of Soils [Last Update: 00]
12. ASTM
D4595 Standard Test Method for Tensile Properties of Geotextiles by the
Wide-Width Strip Method [Last Update: 86 (2001)]
13.
ASTM D5262 Standard Test
Method for Evaluating the Unconfined Tension Creep Behavior of Geosynthetics [Last
Update: 97]
14. ASTM F405 [Last Update: 97] Standard Specification for Corrugated
Polyethylene (PE) Tubings and Fittings
15. ASTM
G51 Standard Test Method for Measuring pH of Soil for Use in Corrosion Testing [Last
Update: 95 (2000)]
C. National Concrete Masonry
Association (NCMA)
1. NCMA
Design Manual For Segmental Retaining Walls, Second Edition, Second Printing
(1997)
2. NCMA
SRWU-1 Determination of Connection Strength Between Geosynthetics and Segmental
Concrete Units
3. NCMA
SRWU-2 Determination of Shear Strength Between Segmental Concrete Units
1.03 DEFINITIONS
A. Backfill: Soil which is used as fill behind the
drainage aggregate, and within the reinforced soil mass (if applicable).
B. Drainage
Aggregate: Material used within (if
applicable), between, and directly behind the concrete retaining wall units.
C. Filter
Fabric: Material used for separation
and filtration of dissimilar soil types.
D. Foundation
Soil: Soil mass supporting the leveling
pad and reinforced soil zone of the retaining wall system.
E. Geosynthetic
Reinforcement: Material specifically fabricated
for use as a soil reinforcement.
F. Global Stability: The general mass movement of a soil
reinforced segmental retaining wall structure and adjacent soil mass.
G. Project Geotechnical Engineer: A registered engineer employed by the Owner
to perform site observations, provide recommendations for foundation support,
and verify soil shear strength parameters.
1.04 SUBMITTALS
A. Submit
the following in accordance with Section 01300:
1. Product Data: Material description and installation
instructions for each manufactured product specified.
2. Shop
Drawings: Retaining wall system design,
including wall elevation views, geosynthetic reinforcement layout, pertinent
details, and drainage provisions. The
shop drawings shall be signed by a registered professional engineer licensed in
the state of wall installation.
3.
Design Calculations: Engineering design calculations prepared in
accordance with the NCMA Design Manual For Segmental Retaining Walls, or the
AASHTO Standard Specifications for Highway Bridges, Section 5.8 (whichever is
applicable). Analysis of global
stability must be addressed and incorporated into the shop drawings.
4.
Samples
a. Furnish
one unit in the color and face pattern specified, if requested.
b. Furnish
12 inch square or larger piece of the geosynthetic reinforcement specified.
5. Test
Reports: Independent laboratory reports
stating moisture absorption and compressive strength properties of the concrete
retaining wall units meet the Project Specifications when tested in accordance
with ASTM C140, Sections 6, 8 and 9.
1.05 DELIVERY, STORAGE AND HANDLING
A. Deliver,
store, and handle materials in accordance with manufacturer's recommendations,
in such a manner as to prevent damage.
Check the materials upon delivery to assure that proper material has
been received. Store above ground on
wood pallets or blocking. Remove
damaged or otherwise unsuitable material, when so determined, from the site.
1. Exposed faces of concrete wall
units shall be free of chips, cracks, stains, and other imperfections
detracting from their appearance, when viewed from a distance of 10 feet.
2. Prevent
mud, wet cement, adhesives and similar materials which may harm appearance of
units, from coming in contact with system components.
1.06 EXTRA MATERIALS
A. Furnish
Owner with 3 replacement units identical to those installed on the Project.
PART 2 -
PRODUCTS
2.01 MATERIALS
A. Concrete
Retaining Wall Units: "Anchor Vertica Pro Retaining Wall Units" as
manufactured under license from Anchor Wall Systems.
1. Physical Requirements
a.
Meet requirements of ASTM C1372, except
the maximum water absorption shall be limited to 7 percent, and unit height
dimensions shall not vary more than plus or minus 1/16 inch from that specified
in the ASTM reference, not including textured face.
b. Unit Face Area: Not less than 0.94 square feet.
Note to
Specifier: In Subparagraph below,
select appropriate entity who will determine color
c. Color:
Selected by the [Architect] [Engineer] [Owner] from manufacturer's full
range of standard colors.
Note to
Specifier: In Subparagraph below,
select straight or beveled face
d. Face
Pattern Geometry: [Straight] [Beveled].
e. Texture: Split Rock Face.
f. Include
an integral concrete shear connection flange/locator.
B. Geosynthetic
Reinforcement: Polyester fiber geogrid
or geotextile, or polypropylene woven geotextile, as shown on the Drawings.
C. Leveling Pad Base
1. Aggregate
Base: Crushed stone or granular fill
meeting the following gradation as determined in accordance with ASTM D448:
Sieve Size Percent Passing
1 inch 100
No. 4 35
to 70
No. 40 10
to 35
No. 200 3 to 10
a. Base
Thickness: 6 inches (minimum compacted
thickness).
2. Concrete
Base: Nonreinforced lean concrete base.
a. Compressive Strength: 500 psi (maximum).
b. Base Thickness: At least 2 inches, but not more than 3 inches.
D. Drainage
Aggregate: Clean crushed stone or
granular fill meeting the following gradation as determined in accordance with
ASTM D448:
Sieve Size Percent Passing
1
inch 100
3/4
inch 75 to 100
No. 4 0 to 60
No. 40 0 to 50
No.
200 0 to 5
E. Backfill: Soil free of organics and debris and consisting
of either GP, GW, SP, SW, or SM type, classified in accordance with ASTM D2487
and the USCS classification system.
1.
Soils classified as SC and CL are considered suitable soils
for segmental retaining walls with a total height of less than 15 feet unless
the Plasticity Index (PI) is 20 or more.
2.
Maximum particle size for backfill is 2 inches.
3.
Unsuitable soils are organic soils and those soils classified
as CH, OH, MH, OL, or PT.
F. Impervious Material: Clayey soil or other similar material which
will prevent percolation into the drainage zone behind the wall.
G. Drainage
Pipe: Perforated or slotted PVC or
corrugated HDPE pipe manufactured in accordance with D3034 and/or ASTM F405.
The pipe may be covered with a geotextile filter fabric to function as a
filter.
H. Construction Adhesive: Exterior grade adhesive as recommended by
the retaining wall unit manufacturer.
PART 3 -
EXECUTION
3.01 EXAMINATION
Note to
Specifier: In Paragraph below, select
appropriate entity
A. Examine the areas and conditions
under which the retaining wall system is to be erected, and notify the
[Architect] [Engineer] [Owner] [Contractor] in writing of conditions
detrimental to the proper and timely completion of the work. Do not proceed with the work until
unsatisfactory conditions have been corrected.
B. Promptly notify the wall design
engineer of site conditions which may affect wall performance, soil conditions
observed other than those assumed, or other conditions that may require a
reevaluation of the wall design.
C. Verify the location of existing
structures and utilities prior to excavation.
3.02 PREPARATION
A. Ensure surrounding structures are
protected from the effects of wall excavation.
B. Excavation support, if required, is
the responsibility of the Contractor, including the stability of the excavation
and it's influence on adjacent properties and structures.
3.03 EXCAVATION
Note to
Specifier: In Paragraph below, select
appropriate entity
A. Excavate to the lines and grades
shown on the Drawings. Over-excavation
not approved by the [Architect] [Engineer] [Owner (or Owner's representative)]
will not be paid for by the Owner.
Replacement of these soils with compacted fill and/or wall system
components will be required at the Contractor's expense. Use care in excavating to prevent
disturbance of the base beyond the lines shown.
3.04 FOUNDATION
PREPARATION
A. Excavate
foundation soil as required for footing or base dimension shown on the
Drawings, or as directed by the Project geotechnical engineer.
B. The
Project geotechnical engineer will examine foundation soil to ensure that the
actual foundation soil strength meets or exceeds that indicated on the
Drawings. Remove soil not meeting the
required strength. Oversize resulting space sufficiently from the front of the
block to the back of the reinforcement, and backfill with suitable compacted
backfill soils.
C. The Project geotechnical engineer will
determine if the foundation soils will require special treatment or correction
to control total and differential settlement.
D. Fill
over-excavated areas with suitable compacted backfill, as recommended by the
Project geotechnical engineer.
3.05 BASE
COURSE PREPARATION
A. Place
base materials to the depths and widths shown on the Drawings, upon undisturbed
soils, or foundation soils prepared in accordance with Article 3.04.
1. Extend the leveling pad
laterally at least 6 inches in front and behind the lowermost concrete
retaining wall unit.
2. Provide aggregate base compacted
to 6 inches thick (minimum).
3. The
Contractor may at their option, provide a concrete leveling pad as specified in
Subparagraph 2.01.C.2, in lieu of the aggregate base.
4. Where a reinforced footing is
required by local code official, place footing below frost depth.
B. Compact
aggregate base material to provide a level, hard surface on which to place the
first course of units.
C. Prepare
base materials to ensure complete contact with retaining wall units. Gaps are not allowed.
3.06 ERECTION
A. General: Erect units in accordance with
manufacturer's instructions and recommendations, and as specified herein.
B. Place
first course of concrete wall units on the prepared base material. Check units for level and alignment. Maintain the same elevation at the top of
each unit within each section of the base course.
C. Ensure that foundation units are in full
contact with natural or compacted soil base.
D. Place concrete wall units side-by-side
for full length of wall alignment.
Alignment may be done by using a string line measured from the back of
the block. Gaps are not allowed between
the foundation concrete wall units.
E. Place
12 inches (minimum) of drainage aggregate between, and directly behind the concrete
wall units. Fill voids in retaining
wall units with drainage aggregate.
Provide a drainage zone behind the wall units to within 9 inches of the
final grade. Cap the backfill and
drainage aggregate zone with 9 inches of impervious material.
F. Install
drainage pipe at the lowest elevation possible, to maintain gravity flow of
water to outside of the reinforced zone.
Slope the main collection drainage pipe, located just behind the
concrete retaining wall units, 2 percent (minimum) to provide gravity flow to
the daylighted areas. Daylight the main
collection drainage pipe through the face of the wall, and/or to an appropriate
location away from the wall system at each low point or at 50 foot (maximum) intervals
along the wall. Alternately, the
drainage pipe can be connected to a storm sewer system at 50 foot (maximum)
intervals.
G. Remove
excess fill from top of units and install next course. Ensure drainage aggregate and backfill are
compacted before installation of next course.
H. Check
each course for level and alignment.
Adjust units as necessary to maintain level and alignment prior to
proceeding with each additional course.
I. Install
each succeeding course. Backfill as
each course is completed. Pull the
units forward until the locating surface of the unit contacts the locating
surface of the units in the preceding course.
Interlock wall segments that meet at corners by overlapping successive
courses. Attach concrete retaining wall
units at exterior corners with adhesive specified.
J. Install
geosynthetic reinforcement in accordance with geosynthetic manufacturer's
recommendations and the shop drawings.
1.
Orient geosynthetic
reinforcement with the highest strength axis perpendicular to the wall face.
2. Prior to
geosynthetic reinforcement placement, place the backfill and compact to the
elevation of the top of the wall units at the elevation of the geosynthetic
reinforcement.
3. Place
geosynthetic reinforcement at the elevations and to the lengths shown on the
Drawings.
4. Lay
geosynthetic reinforcement horizontally on top of the concrete retaining wall
units and the compacted backfill soils.
Place the geosynthetic reinforcement within one inch of the face of the
concrete retaining wall units. Place
the next course of concrete retaining wall units on top of the geosynthetic
reinforcement.
5.
The geosynthetic
reinforcement shall be in tension and free from wrinkles prior to placement of
the backfill soils. Pull geosynthetic
reinforcement hand-taut and secure in place with staples, stakes, or by
hand-tensioning until the geosynthetic reinforcement is covered by 6 inches of
loose fill.
6. The
geosynthetic reinforcements shall be continuous throughout their embedment
lengths. Splices in the geosynthetic
reinforcement strength direction are not allowed.
7. Do
not operate tracked construction equipment directly on the geosynthetic
reinforcement.
At least 6
inches of compacted backfill soil is required prior to operation of tracked
vehicles over the geosynthetic reinforcement.
Keep turning of tracked construction equipment to a minimum.
8. Rubber-tired equipment may pass
over the geosynthetic reinforcement at speeds of less than
5 miles per
hour. Turning of rubber-tired equipment
is not allowed on the geosynthetic reinforcement.
3.07 BACKFILL PLACEMENT
A. Place
reinforced backfill, spread and compact in a manner that will minimize slack in
the reinforcement.
B. Place
fill within the reinforced zone and compact in lifts not exceeding 6 to 8
inches (loose thickness) where hand-operated compaction equipment is used, and
not exceeding 12 inches (loose thickness) where heavy, self-propelled
compaction equipment is used.
1. Only
lightweight hand-operated compaction equipment is allowed within 4 feet of the
back of the retaining wall units. If
the specified compaction cannot be achieved within 4 feet of the back of the
retaining wall units, replace the
reinforced soil in this zone with drainage aggregate material.
Note to
Specifier: In Paragraph below, select
revised modified Proctor densities if necessary, in lieu of standard Proctor
densities specified
C. Minimum
Compaction Requirements for Fill Placed in the Reinforced Zone
1. Walls Less Than 15 Feet
High: Compact to 95 percent of the
soil's standard Proctor maximum dry density (ASTM D698) [modified Proctor
maximum dry density (ASTM D1557)] for the entire wall height
2. Walls 15 Feet High BUT NOT MORE
THAN 30 Feet High: Change compaction
requirements to 98 percent of the soil's standard Proctor maximum dry density
(ASTM D698) [modified Proctor maximum dry density (ASTM D1557)] for depths
below 15 feet.
3. Walls Over 30 Feet High: Change compaction requirements to 100
percent of the soil's standard Proctor maximum dry density (ASTM D698)
[modified Proctor maximum dry density (ASTM D1557)] for depths below 30 feet.
4. Increase compaction requirements
for retaining walls with slope heights at the back of the reinforced soil zone
greater than 5 feet above the top of wall.
Verify compaction requirements with Project geotechnical engineer.
5. Utility
Trench Backfill: Compact utility trench
backfill in or below the reinforced soil zone to
98 percent of
the soil's standard Proctor maximum dry density (ASTM D698) [modified Proctor
maximum dry density (ASTM D1557)], or as recommended by the Project
geotechnical engineer. If the height
from the utility to finish grade is higher than 30 feet, increase compaction to
100 percent of
the standard Proctor density [modified Proctor density].
a. Utilities must be properly designed (by
others) to withstand all forces from the retaining wall units, reinforced soil
mass, and surcharge loads, if any.
6. Moisture Content: Within 2 percentage points of the optimum
moisture content for all wall heights.
7. These specifications may be
changed based on recommendations by the Project geotechnical engineer.
a. If changes are required, the Contract Sum
will be adjusted by written Change Order.
D. At
the end of each day's operation, slope the last level of compacted backfill
away from the interior (concealed) face of the wall to direct surface water
runoff away from the wall face.
1. The General Contractor is
responsible for ensuring that the finished site drainage is directed away from
the retaining wall system.
2. In addition, the General
Contractor is responsible for ensuring that surface water runoff from adjacent
construction areas is not allowed to enter the retaining wall area of the construction
site.
E. Refer to Article 3.10 for compaction
testing.
3.08 CAP
UNIT INSTALLATION
A.
Apply adhesive to the top surface of the
unit below and place the cap unit into desired position.
B. Cut
cap units as necessary to obtain the proper fit.
C. Backfill
and compact to top of cap unit .
3.09 SITE
CONSTRUCTION TOLERANCES
A. Site Construction Tolerances
1.
Vertical
Alignment: Plus or minus 1-1/2 inches
over any 10-foot distance, with a maximum differential of 3 inches over the
length of the wall.
2. Horizontal
Location Control From Grading Plan
a. Straight Lines: Plus or minus 1-1/2 inches over any 10-foot distance.
b. Corner and Radius Locations: Plus or minus 12 inches.
c. Curves and Serpentine Radii: Plus or minus 2 feet.
3. Immediate Post Construction Wall
Batter: Within 2 degrees of the design
batter of the concrete retaining wall units.
4. Bulging: Plus or minus 1-1/4 inches over any 10-foot
distance.
3.10 FIELD QUALITY CONTROL
A. Installer
is responsible for quality control of installation of system components. Employ a qualified independent third party
to verify the correct installation of system components in accordance with
these specifications and the Drawings.
B. The
Owner, at their expense, will retain a qualified professional to perform
quality assurance checks of the installer's work.
C. Correct
work which does not meet these specifications or the requirements shown on the
Drawings at the installer's expense.
D. Perform
compaction testing of the reinforced backfill placed and compacted in the
reinforced backfill zone.
1. Testing Frequency
a. One test for every 2 feet (vertical) of fill
placed and compacted, for every 50 lineal feet of retaining wall.
b. Vary compaction test locations to cover the
entire area of the reinforced soil zone, including the area compacted by the
hand-operated compaction equipment.
3.11 ADJUSTING
AND CLEANING
A. Replace
damaged units with new units as the work progresses.
B. Remove
debris caused by wall construction and leave adjacent paved areas broom clean.
Note to
Specifier: Include Article 3.12 ONLY
for municipal work when required
3.12 MEASUREMENT AND PAYMENT
A. Measurement
of segmental retaining wall shall be on an installed square foot basis computed
on the total face area of wall installed.
Wall face area includes the bottom of the base course to the top of the
wall, and the entire length of the wall.
B. Payment
for the wall will be made on a square foot basis at the agreed upon Contract
Unit Price.
1. Payment
should be considered full compensation for labor, materials, equipment and
testing required to install the wall in accordance with these specifications
and the Drawings.
2. Quantities
may vary from that shown on the Drawings depending on existing topography. Change to the total quantity of wall face
area will be paid or withheld at the agreed upon Contract Unit Price.
END OF SECTION